Where can robotaxi depots actually get power?

Depots need megawatts, and the grid says how many it can spare. We put ride-hail demand, large parking lots and the grid's own published numbers on one map.

By XoomPark ·

SF lots with room for 1 MW

41 of 126

Lots over 1 acre, PG&E 2026 forecast

SF riders on tight grid

65%

Of weekly Uber and Lyft pickups and drop-offs (2016)

PG&E new-circuit wait

1,142 days

Average of 49 projects, 2023–24

Austin power vs hub price

+27%

$42.57 vs $33.55/MWh, Oct 12–Oct 19

The map

Squares are about 440 m. We show large lots per square, never single lots. Tap a square, substation or line for its numbers.

41 of 126 large lots have room for 1 MW in PG&E's 2026 forecast.

  • Large lots, room for 1 MW
  • Large lots, not enough room
  • Large lots, no public number
  • Ride-hail pickups and drop-offs (2016)
  • Substation PG&E flags by 2027
  • Other PG&E substation

San Francisco: the busy part is the tight part

PG&E publishes, for every feeder and substation transformer bank in San Francisco, its rating and its forecast peak load for each year to 2040.1 Rating minus the 2026 forecast is the spare capacity. We took the 126 surface parking lots of an acre or more in the city,2 found the PG&E line each one sits next to, and kept the smaller of the feeder's and the substation's spare capacity. That is the room a depot there could plug into without an upgrade, on PG&E's own forecast.

41 lots have room for 1 MW. 22 have room for 2 MW and 14 for 5 MW. For 45 more, PG&E withholds the load figure. 29 are not near a PG&E San Francisco feeder at all: the Presidio, Treasure Island and lots just over the county line. The feeder, not the substation, was the tighter of the two for 49 of the 52 lots with numbers.

1 MW is not a lot of depot. Running flat out for 24 hours it delivers 24 MWh, enough for at most 286 robotaxi-days at 83.8 kWh each (the bridge section shows where that figure comes from).

The demand sits where the grid is tightest. PG&E lists a capacity need by 2027, or has a transformer bank already over its rating, at 5 of the 19 San Francisco substations in its data: Potrero, Embarcadero, Larkin, Mission and Hunters Point.1 The only public count of ride-hail trips in San Francisco is the city transportation authority's: Uber and Lyft pickups and drop-offs by zone, for a typical week in late 2016.4 Of the 2,199,419 weekly pickups and drop-offs we could place on a PG&E feeder, 1,428,811 (65%) sit on those 5. Robotaxis serve the same trips, so a depot near the riders lands on the tightest part of the grid.

Austin: no headroom data, so watch the wires

Austin Energy is a city-owned utility and publishes no feeder or substation headroom. ERCOT, which runs the Texas grid, does publish every transmission limit that binds in its five-minute dispatch,5 the substations at each end,7 and the price at Austin's load zone.6

From Oct 12 to Oct 19, 2 lines into Austin Energy substations bound. The one between Magnesium Plant and Northland bound in 65 of 2,165 dispatch runs (3%), at an average shadow price of $462/MWh; the one between Burleson and Hi Cross bound in 6. Austin's load zone averaged $42.57/MWh against $33.55 for the ERCOT hub average, 27% more.

Austin Energy's own slides say the rest. Summer peak is 3,110 MW against about 800 MW of local generation, so the city leans on imports, and $500M of transmission upgrades are planned.10 On large new loads across ERCOT, it says transmission planning, approvals and construction "can take 3-5+ years".9 A depot is smaller than the data centers that sentence is about, but Austin publishes no depot-sized timeline.

The bridge: what a battery buys while you wait

PG&E's own reports put numbers on the wait. EV charging service jobs took 467 days end to end on average.12 When the site needed a new circuit or a circuit upgrade, PG&E averaged 1,142 days, about 37.5 months. Substation upgrades averaged 1,307.11

A bridge is energy that arrives some other way: a battery trucked in, or a big battery on site filled when the grid has room. Pick a fleet size and a wait below. The constants come from Waymo,14 the EPA,15 Xos16 and Tesla.17

Bridge calculator

One robotaxi-day is the energy one vehicle uses in a day. Change the scenario; the constants are sourced.

Utility wait the site faces
Energy one robotaxi uses a day83.8 kWh

190 miles a day (Waymo: 4M+ miles a week across 3,000 vehicles) × 44 kWh per 100 miles (EPA, Jaguar I-PACE, at the wall)

Energy 20 robotaxis need a day1.68 MWh
One mobile battery fill covers7.5 robotaxi-days

Xos Hub, 630 kWh, 4 × 150 kW ports (vendor spec)

Mobile fills needed a day2.7
One on-site battery cycle covers46 robotaxi-days

Tesla Megapack 2 XL, 3,854 kWh. Refilling it takes 4.2 MWh from the grid at 91.7% round trip, so it needs some off-peak power

On-site battery cycles needed a day0.43
Months the site runs on a mobile bridge instead of waiting37.3

1,142 days of wait minus 7 days to deploy (SparkCharge, vendor claim)

The arithmetic points one way. Twenty robotaxis need about 2.7 mobile battery fills a day; a hundred need 13. Trucks can carry a small stop inside the zone through a 37.5-month wait. They can't carry a whole edge depot. PG&E also offers Flex Connect, which lets a site connect now under hourly limits while upgrades are built, for sites facing waits of more than 12 months.13

Five more cities: how fast can a depot open?

A site opens when it has both a permit and power. Cities publish their permit records, so we measured the days from application to issue for commercial EV charger permits since 2023. For power, California's utilities file their average time to energize an EV charging job with the CPUC. The other utilities publish none.

Where both are public, power sets the date, not the permit. Permits take days to about two months. SDG&E averaged 347 business days to energize an EV job and SCE 571, about 1.4 and 2.3 years.2019

Los Angeles, SCE areas

Southern California Edison

EV charger permit

96% without plan check

362 commercial EV permits issued; 14 went through plan check, and the 14 with both dates took a median 68 days.23

Utility power

571 business days

Average for SCE EV jobs, median 518. About 2.3 years.19

Sets the date: Power

Los Angeles, LADWP areas

LA Department of Water and Power

EV charger permit

Same as above

The city of LA issues these permits for both utilities' areas.23

Utility power

Not published

LADWP is city-owned and files no energization times.

Sets the date: Unknown

San Diego

SDG&E

EV charger permit

62 days

Median of 377 EV charging approvals issued since 2024, all property types.24

Utility power

347 business days

Average of 34 SDG&E EV jobs. About 1.4 years.20

Sets the date: Power

Miami

Florida Power & Light

EV charger permit

70 days

City of Miami, median of 118 commercial EV charging permits.25 Miami-Dade County's median is under a day (94 permits).26

Utility power

Not published

FPL publishes no energization times and no capacity map.

Sets the date: Unknown

Dallas

Oncor

EV charger permit

7 days

Median of only 12 commercial car-charging permits, 2023 to 2024. Dallas stopped publishing permit data in Nov 2024.27

Utility power

Not published

Oncor publishes its large-load queue, not time to energize.

Sets the date: Unknown

Atlanta

Georgia Power

EV charger permit

No reliable data

The city's permit feed has no issue date and no electrical permits.28

Utility power

Not published

Georgia Power publishes no energization times.

Sets the date: Unknown

Where power exists matters as much as how fast. Of the 100 Los Angeles sites our depot look-alike screen ranks highest, 38 sit in SCE areas, and 28 of those have a circuit with room for 1 MW or more on SCE's grid-capacity map.21 In LADWP areas, 47 sit by a 34.5 kV line with more than 7.5 MW to spare, which usually means building your own transformer yard, and 13 only by local 4.8 kV lines that offer at most 600 kW.22

Dallas, like Austin, shows up only in ERCOT's data. From Oct 14 to Oct 21, the North load zone that covers Dallas averaged $28.74/MWh against $30.46 for the hub average, 6% cheaper. Austin paid 22% more the same week.6

Method

  • Candidate sites: OpenStreetMap parking areas of at least 1 acre (4,047 m²), excluding underground, multi-storey, rooftop and street parking. They are lots big enough to hold a depot, not lots for sale or ours. Shown only as counts per square.
  • Demand: we count only lots inside a published robotaxi service area:3 all 126 in San Francisco, 582 of 1,053 in Austin. San Francisco also shows ride-hail demand: SFCTA's weekly Uber and Lyft pickups plus drop-offs per zone, placed at each zone's centre.4 Austin has no public ride-hail trip data, so its demand is the service area alone.
  • SF headroom: each lot and each demand zone's centre is matched to the nearest PG&E line section within 300 m, which gives its feeder; the feeder id gives the substation. Feeder room is rating minus 2026 forecast peak. Substation room is the same summed over its banks. A lot's room is the smaller of the two.1
  • Tight grid (SF): a substation where PG&E's grid-needs data lists a capacity need in 2027 or earlier for any bank or feeder, or where a bank's 2026 forecast is over its rating.
  • Austin: ERCOT binding constraints whose end stations are Austin Energy substations, from ERCOT's bus mapping. 61 of 66 substations matched to OpenStreetMap by name. Lines on the map are drawn straight between the two substations, not along the real route. Prices are 15-minute settlement prices for LZ_AEN and HB_HUBAVG over the same week.
  • Days to open: permit days are calendar days from application to issue, median, for permits issued since 2023 whose description mentions EV charging and that the city flags as commercial (San Diego has no flag, so all property types count). Power is the utility's own filed average for EV charging jobs, in business days, read as years at 250 working days a year.
  • LA power: for each of the 100 top-ranked candidate sites, the best circuit within about 150 m on SCE's load capacity map or LADWP's capacity map, taking the low end of LADWP's ranges.
  • Bridge: 190 miles a day is Waymo's weekly miles divided by its fleet and seven days. EPA's 44 kWh per 100 miles is measured at the wall, so charging losses are in it.

Caveats

  • Spare capacity on a forecast is a screening number, not a connection offer. Only PG&E or Austin Energy can say what a specific site can get, and hourly limits can allow more than the peak-hour figure.
  • PG&E withholds load data for feeders with few customers, so many lots show no number. Downtown's networked grid works differently from a radial feeder.
  • The ride-hail counts are from November and December 2016 and cover trips within San Francisco only. They are the latest public trip data; the CPUC and the companies have not released newer zone counts. Demand has grown and shifted since, so read them as where riders cluster, not how many there are now.
  • One October week of ERCOT data. Constraints bind most in summer. ERCOT's public download keeps about a week, so we will re-pull it monthly.
  • Utility averages include time the customer spends on design and paperwork. Most LA EV permits were issued without plan check, and the data has no application date for them, so we report their share, not their days.
  • Bridge figures leave out cost, permits, and the time to charge each car, and the deploy time is a vendor's claim.
  • PG&E data is PG&E's, shown here aggregated and credited. ERCOT allows its public data in analyses.8 OpenStreetMap data is available under the ODbL.

Sources

  1. PG&E Grid Resource Integration Portal (GRIP): grid needs, feeder and bank loading, line sections
  2. OpenStreetMap contributors, via Overpass (parking, land use, substations), ODbL
  3. avmap.io open dataset of robotaxi service areas (MIT)
  4. SFCTA, TNCs Today: Uber and Lyft pickups and drop-offs by zone, Nov-Dec 2016
  5. ERCOT NP6-86-CD, SCED shadow prices and binding transmission constraints
  6. ERCOT NP6-905-CD, settlement point prices at load zones and hubs
  7. ERCOT NP4-160-SG, settlement points and electrical bus mapping
  8. ERCOT website terms of use
  9. Austin Energy, Connecting Large Customers, Feb 2026
  10. Austin Energy, Transmission, Apr 2026
  11. CPUC energization timelines workshop, Jun 30 2025 (PG&E upstream capacity performance, slide 33)
  12. PG&E biannual energization report under D.24-09-020, filed Apr 1 2025
  13. PG&E Flex Connect
  14. Waymo, Advice, not control: the role of remote assistance, Feb 17 2026
  15. fueleconomy.gov, 2019 Jaguar I-PACE
  16. Xos Hub mobile charger specifications
  17. Tesla Megapack 2 XL datasheet, rev 2.0, Nov 13 2025
  18. SparkCharge (deployment time, vendor claim)
  19. SCE biannual energization report under D.24-09-020, filed Apr 1 2026 (Table 4)
  20. SDG&E biannual energization report, Sept 30 2026 (Table 3)
  21. SCE DRPEP Integration Capacity Analysis, circuit segments (load capacity)
  22. LADWP Power Capacity map, available capacity by line
  23. LADBS electrical permits submitted, 2020 to present (data.lacity.org)
  24. City of San Diego, development permit approvals (data.sandiego.gov)
  25. City of Miami, building permits since 2014 (CC BY 4.0)
  26. Miami-Dade County, building permits issued, previous two years to present
  27. City of Dallas, new permits 2008 to 2024
  28. City of Atlanta, building permit tracker

Data as of October 21, 2026. Sources are public and free; none needed a login. XoomPark isn't affiliated with the companies named here.