How to build an AV fleet charging schedule that has every car ready by morning

Work backward from the morning: the energy each car needs back, the hours in your cheap window and the power your site can draw. Then order the cars so none waits behind a full one.

By Greg Bessoni, Founder and CEO, XoomPark ·

An overnight schedule comes down to three numbers: the energy each car needs back, the hours in your cheap window and the power your site can draw. Divide the night's energy by the window's hours and you have the least power the yard needs. Then order the cars by when each one leaves, so no car sits on a charger it no longer needs.
One night at a 40-car depot. Assumes 150 miles a car at EPA's 48 kWh per 100 miles and 90% charging efficiency; your miles and window will differ.
StepNumberHow we got it
Energy into each battery72 kWh150 mi × 48 kWh per 100 mi1
Energy from the grid, per car80 kWh72 kWh ÷ 0.90 charging efficiency5
Energy for the whole yard3,200 kWh40 cars × 80 kWh
Least site power for a 7-hour window457 kW3,200 kWh ÷ 7 hours
Level 2 chargers at 19.2 kW, fully used243,200 kWh ÷ (19.2 kW × 7 h)
DC fast chargers at 150 kW, fully used43,200 kWh ÷ (150 kW × 7 h), rounded up

How much energy does each robotaxi need back?

Miles driven times the car's energy use, plus what the charger loses on the way in. A car rated at 48 kWh per 100 miles that drove 150 miles needs 72 kWh in the battery, and about 80 kWh from the grid.

Start from the EPA rating, not the brochure. EPA lists a 2026 Hyundai Ioniq 5 under the name "Robo taxi" at 48 kWh per 100 miles and 168 miles of range.1 The ordinary rear-drive 2026 Ioniq 5 is rated at 30 kWh per 100 miles and 318 miles.2 Same body, 60% more energy per mile. EPA doesn't say why, but a robotaxi carries sensors and computers the regular car doesn't, so plan from the robotaxi figure if your cars have one.

EPA energy ratings for cars common in ride-hail and robotaxi fleets, from fueleconomy.gov.
CarkWh per 100 miGrid energy for 150 mi at 90% efficiency
2026 Hyundai Ioniq 5 "Robo taxi"14880 kWh
2024 Jaguar I-Pace EV400103965 kWh
2026 Hyundai Ioniq 5 RWD23050 kWh
2027 Chevrolet Bolt112847 kWh

Charging isn't free of losses. Fueleconomy.gov puts battery charging efficiency at 84% to 93%,3 and NREL's national charging study assumes 90% for AC charging.5 The meter at your service entrance sees the grid figure, so that is the number your schedule and your power bill run on.

Miles are the number you control least. Use a week of your own data, take each car's worst day rather than the average, and the schedule will hold on a busy Saturday.

How many hours does one charger give you in a night?

Hours per car are the energy it needs divided by the charger's power. At 19.2 kW, an 80 kWh refill takes about 4.2 hours, so one Level 2 charger finishes one car and half of another in a 7-hour window.

The Department of Energy's Alternative Fuels Data Center puts Level 2 equipment at 2.9 to 19.2 kW, on 40 to 80 amp circuits. DC fast chargers go up to 500 kW, but AFDC notes many EVs can't take more than 200 kW.4 The car sets the ceiling as often as the charger does.

DC charging also slows as the battery fills. NREL's 2030 network study describes the car's battery management system tapering its charge rate as state of charge rises, to protect the pack.5 Fueleconomy.gov puts even a fast charge to 80% at about 30 minutes.3 So a DC charger is quick from 20% to 80% and slow after. A car that has to go above 80% is usually better finished on Level 2, or left to finish while nobody else is waiting.

Hours per car for an 80 kWh refill, and full charges per charger in a 7-hour window. DC hours assume the car can take the charger's full power, which many can't near a full battery.
ChargerHours per 80 kWh carFull charges in 7 hours
Level 2, 11.5 kW (48 A)7.01
Level 2, 19.2 kW (80 A)4.21, plus 54 kWh into a second car
DC fast, 50 kW1.64
DC fast, 150 kW0.5 or moreUp to 13 in theory; the taper and moving cars cut that

What sets the power a depot needs overnight?

The window, not the charger count. Nightly energy divided by window hours is the least power the depot must draw the whole time. For 3,200 kWh in 7 hours that is 457 kW, whether it comes from 24 Level 2 chargers or 4 DC chargers.

This is the number to take to your utility and your electrician first. Shorten the window to 6 hours and the floor rises to 533 kW. Stretch it to 9 hours and it drops to 356 kW. Chargers only decide whether you can reach that floor, and how many times someone or something has to move a car.

Wiring is sized above the charger rating. EV charging counts as a continuous load, and the National Electrical Code requires the wiring and overcurrent protection for a charger to be 125% of its continuous output, as Pacific Northwest National Laboratory summarizes it.8 A 19.2 kW, 80 amp charger needs a 100 amp circuit. Twenty-four of them add up to a service that is easy to oversize if every charger is counted at full power.

In what order should the robotaxis charge?

Earliest departure first, and never leave a full car on a charger. A car that leaves at 5:30 a.m. charges before one that leaves at 8, and the moment a car reaches its target it moves off for the next one.
  • Sort by departure time, then by energy needed. The car that leaves first and needs the most starts first.
  • Set a target, not 100%. Most cars only need what the next day's miles require plus a reserve; every kWh above that holds a charger for nothing.
  • Put the low cars on DC and the nearly full cars on Level 2. DC is fast below 80% and slow above it.5
  • Count the moves. Every swap is a person walking the yard or a car repositioning itself. A schedule that needs 40 moves at 2 a.m. fails on the night someone calls in sick.
  • Leave one charger spare. A charger that faults at midnight should cost you one car's top-up, not the morning.

The waste in most yards isn't a slow charger. It is a full car still plugged in while an empty one waits. A full car holding a charger for two hours is two hours of 19.2 kW, about 38 kWh, that someone else didn't get.

How do you keep the whole yard under one power limit?

Networked chargers take a power limit from your software and share it. With OCPP charging profiles a management system can cap what each charger draws over time, so the yard never asks the utility for more than you planned.

AFDC's fleet guidance says networking allows smart charging: scheduling charging at night, staggering vehicles and using lower off-peak rates, and it advises choosing chargers on OCPP 1.6 or higher so you can switch networks without new hardware.6 The Open Charge Alliance describes charging profiles as a schedule that sets how much power an EV may draw over time, including a default profile that allows charging only in off-peak hours.7

The payoff can be large. NREL found charge management could cut peak charging load at school bus depots by up to 77%.9 Buses aren't robotaxis, and nobody has published the same figure for a robotaxi yard, but the mechanism is the same: the cars are parked longer than they need to charge, so they don't all have to charge at once.

A lower cap means a smaller service and a lower demand charge. Demand charges bill your single busiest 15 or 30 minutes, so letting every charger start at the same moment at 11 p.m. can cost more than the energy itself.

We worked one night for a 40-car robotaxi yard

Using EPA's robotaxi rating, 150 miles a car and a 7-hour window, the yard needs 3,200 kWh and at least 457 kW. Twenty-four Level 2 chargers can only just deliver that if none ever sits idle, so we would plan 28 to 30.

Our method: EPA's 48 kWh per 100 miles for the Ioniq 5 robotaxi,1 NREL's 90% AC charging efficiency,5 and every car returning by 10 p.m. Twenty-four Level 2 chargers at 19.2 kW can supply 3,226 kWh in 7 hours, just over the 3,200 needed, but only if every charger is busy every minute. That leaves no room for a late car, a faulted charger or a move that takes ten minutes. In practice we would plan 28 to 30 chargers, or set the window an hour longer.

Four 150 kW DC chargers can also supply the energy, but they put the whole night's power through four plugs, which means a swap somewhere in the yard about every 12 minutes all night. The Level 2 yard needs about 16 swaps in the night; the DC yard needs about 36. For a yard where cars move themselves, DC is easier. For a yard where people move them, Level 2 is.

Your tariff may give you more than 7 hours. PG&E's business EV rate prices 9 p.m. to 9 a.m. as off-peak every day, a 12-hour window,12 and NV Energy's EV recharge period runs from 12:01 a.m. to noon.13 Over 12 hours the same yard needs only 267 kW, and every charger has slack for a late car.

When an overnight schedule is the wrong plan

  • Your cars run all night. If your service runs around the clock, there is no 7-hour window with every car parked. Plan staggered charging through the day and night instead, and size for the busiest hour.
  • Your cheapest hours are in the middle of the day. PG&E's cheapest period is 9 a.m. to 2 p.m.12 Check your time-of-use rate before you assume night is cheap.
  • Your service can't reach the floor. If 3,200 kWh over 7 hours needs 457 kW and your utility can give you 300, no schedule fixes that. You need a longer window, fewer cars per site or a second site.
  • You can't staff the moves. If nobody is on site at 2 a.m. and the cars can't reposition themselves, plan one car per charger and stop.

If the depot can't hold enough chargers, the cars can charge elsewhere. XoomPark arranges fleet charging at existing stations in the hours their stalls sit unused, never blocks a station's regular customers and never pushes the station past its monthly peak; when the station fills, the robotaxi leaves.

Questions depot managers ask

How long does a robotaxi take to charge to 80%?

On DC fast charging, about 30 minutes for many cars, according to fueleconomy.gov.3 On Level 2 it is hours: an 80 kWh refill at 19.2 kW takes about 4.2 hours. The car's own charging limit often sets the real speed.

Level 2 or DC fast for an overnight depot?

If cars are parked 7 hours or more and people move them, Level 2 usually fits: it needs fewer moves and less peak power per plug. DC fits yards with short windows or cars that reposition themselves. Both need the same total energy.

Should robotaxis charge to 100% every night?

Only if the next day's miles need it. DC charging slows as the battery fills,5 so the last 20% holds a charger longest. Set a target per car from its next shift.

What software runs the schedule?

A charging management system on networked chargers. AFDC advises chargers on OCPP 1.6 or later, so the charging network can be switched without new hardware.6 The software sets per-charger power limits with OCPP charging profiles.7

How much power does a robotaxi depot need?

At least the night's energy divided by the hours you can charge. Forty cars needing 80 kWh each in a 7-hour window need 457 kW all night. See where robotaxi depots get their power.

Authorship

Written by Greg Bessoni in collaboration with Claude Opus 5.5

Role breakdown: Strategy, structure and final verification by Greg Bessoni; research synthesis and draft prose by Claude Opus 5.5.

About the author

Greg Bessoni is the founder and ceo, xoompark. He writes about fleet operations, curb logistics and AV infrastructure.