Waymo has 28 depot and charging sites on public record in 15 US metros, 10 of them operating. Most sit in industrial areas at the edge of the service zone, often near an airport.

By Greg Bessoni, Founder and CEO, XoomPark ·

XoomPark is independent and is not affiliated with Waymo LLC, Alphabet Inc. or any company named here.

Short answers about Waymo depots
QuestionShort answer
Where do Waymos go at night?Back to a depot to charge and get cleaned, or to a nearby lot to wait for the morning rush.
Where do Waymos charge?Mostly at their own depots. In newer cities, also at public fast chargers until dedicated charging is built.
Who runs the depot?Waymo in San Francisco and San Antonio. Partners elsewhere: Moove in Phoenix and Miami, Avis Budget Group in Dallas, Avomo in Austin and Atlanta, Flexdrive by Lyft in Nashville.
How many depots exist?28 sites on public record in 15 metros, 10 operating.

Where do Waymos go at night?

To the depot, mostly. Waymo’s San Francisco depot sits in the Bayview industrial corridor and is widely described as the country’s largest operating robotaxi depot. Workers plug the cars in, clean the interiors, and do routine maintenance such as brakes and fluids, plus Waymo-specific work like replacing lidar and other sensors.1

Not every car goes home at the same time. Fleets thin out overnight as demand drops, and the cars that stay out wait on lots closer to riders. That is where the trouble has come from. In August 2024, Waymo cars waiting on a lot at 2nd and Harrison Streets in San Francisco honked at each other while backing into spaces, with neighbors reporting a peak around 4 a.m. Waymo pushed a software fix on August 13, 2024, and the cars then honked in the cul-de-sac next door until a second fix.1

The pattern is the point. A robotaxi has nowhere to be between 1 a.m. and 6 a.m. except a depot or a lot, and whichever one it picks has neighbors.

Depot Daily

The lots and yards that could become the next depot, in your market.

Get Depot Daily, free

Lots and yards for lease that could hold a robotaxi depot, in your market, each scored against the real depots. Your first market is free.

Your markets

Pick at least one. Your first market is free.

Free for one market. No card. One-click unsubscribe in every email.

Where do Waymos charge?

At depots first. Waymo has said that as its operations in a city mature, it builds its own charging and prioritizes dedicated charging, and that until then it also uses public stations and tries to limit and stagger its use.1 That is when drivers at public fast chargers start noticing the robotaxis in the queue.

The charging behind the depots is large:

  • San Francisco. In 2022 Waymo’s depot there had 19 direct-current (DC) charging stations with more than 2 megawatts of total load, one of the largest charging sites in the city at the time.1
  • Dallas. The permanent depot Avis Budget Group is building has about 10 Alpitronic HYC-400 chargers with four handles each, roughly 40 fast-charging points.2
  • Nashville. Flexdrive by Lyft says its 80,000-square-foot depot has dozens of chargers that can support hundreds of autonomous vehicles, and that Waymo vehicles would move in from October 12, 2026.1

Every Waymo depot on public record, by metro

We count 28 Waymo depot, service and charging sites on public record across 15 metros: 10 operating, 1 under construction, 1 permitted, 6 planned and 10 reported but unconfirmed.1 We show each site by general area only, never a street address; the ones with no published location are listed by city.

The map shows Waymo’s sites; click a city to list them, or a pin for its status and source. The full robotaxi depot map adds every other fleet and charging operator on record.

Waymo depot map

12 sites on the map in 9 cities · 16 reported, location not published

See who runs each depot

Company names are for approved members. Create a free account and ask for access; we approve by hand, usually within a day. Your request includes Depot Daily for your market, free.

Sign up for access

Have an account? Sign in. Just want the newsletter? Get Depot Daily.

Each square marks a general area, not a site

Waymo

Reported, location not published

Not on the map and not counted in a city above.

Austin · 2

Dallas · 2

Los Angeles · 2

Miami · 2

Phoenix · 2

Atlanta · 1

Denver · 1

Houston · 1

Nashville · 1

Orlando · 1

San Diego · 1

Each square marks a general area about 3 miles across, never a building. We don’t publish depot addresses. Sites with no published location are listed by city under Reported. Open the full robotaxi depot map.
Waymo depot, service and charging sites on public record, by metro
MetroArea on recordStatusWho runs it
San FranciscoBayview industrial areaOperatingWaymo, with contractors
Los AngelesSawtelle, West LA, plus satellite lotsReportedNot published
Santa MonicaTwo charging lots near homesOperating, in litigationCharging operator Voltera
PhoenixSouth of the downtown Warehouse District; service sites in Mesa and ChandlerReportedWaymo, with fleet partner Moove
AustinSoutheast AustinOperatingAvomo
DallasThree sites: a temporary depot in a West Dallas commercial park and an Avis-linked depot in East Dallas, no addresses published3; the permanent depot under construction, under 5 miles from Love Field2Two operating; one under constructionAvis Budget Group
HoustonGreater Fifth WardOperatingNot published
San AntonioNortheast SideOperating (Waymo, Nov 3 2026)Waymo
AtlantaAbout 5 miles north of downtownOperatingAvomo
MiamiWynwood, near the Design District; a second site permitted next to Miami International Airport. No addresses publishedOperating and permittedMoove
NashvilleNear Nashville International Airport, plus a smaller micro-depot in the cityOpened Oct 2026; micro-depot reportedFlexdrive by Lyft
TampaNear Tampa International AirportPlanned (reported lease)Not published
Washington, D.C.Northeast D.C.: a service facility in Langdon and a charging depot in Ivy CityPlannedNot published
San DiegoNot publishedPlannedElement Mobility
Denver, OrlandoNot publishedPlanned (Denver), reported (Orlando)Not published

Why Waymo depots sit at the edge of the city

Land, power and neighbors. A depot needs acres, megawatts and a use the city will permit around the clock, and all three are cheapest in industrial areas near airports and rail lines. The cost is distance: every car that goes back to the depot drives there empty.

Santa Monica shows what happens when a charging site sits near homes. Waymo began charging at two lots near homes in 2024. Neighbors complained about noise and late-night work, and in November 2025 the City Council voted 6-0 to declare the lots a public nuisance and ordered overnight operations stopped. City staff measurements found the noise did not break the city’s noise ordinance, so the case rests on nuisance law instead. Waymo sued. In July 2026 a judge barred use of the lots between 11 p.m. and 6 a.m., and an appeals court then stayed that order while the case continues.1

Dallas shows the other constraint, power. While its permanent depot is built, Waymo charges its Dallas fleet on temporary fast chargers mounted on skids and powered by Aggreko generators, not a grid connection.2 The fleet was already running driverless service around the clock, and it was waiting on the grid.

The cost of the trip back

An empty drive to the depot is deadhead: miles with no rider and no fare. An infrastructure founder told The Road to Autonomy that under today’s depot model a car can be out of service for about two hours per servicing run, up to three times a day.4

Here is the arithmetic with the assumptions in the open. Take an 18-hour operating day and one paid trip per hour. Two depot runs of two hours each remove four trips, about a fifth of the day. Three runs remove six, a third. Waymo does not publish trips per vehicle or depot cycle times, so read this as a shape, not a measurement. The loss grows with distance to the depot and with how often the car has to go.

That is why the next layer is small sites inside the service zone: a lot or garage near riders where a car can top up during a lull instead of crossing town. We worked through the full model in Six Lost Hours a Day, and through where the grid has room for in-zone charging in Where can robotaxi depots actually get power?

We use your unused stalls, never fill them so a retail customer can’t charge, and never make you go over your monthly peak.

What the public record leaves out

We built our count from public records, field reports and news coverage, rebuilt on November 6, 2026.1 Of 28 Waymo records, 10 are confirmed operating and 10 are reported but unconfirmed. We publish none of their addresses: the map shows each by general area.

Waymo depot records by status
StatusRecordsWhat it means
Operating10Seen in use by a reporter, field observer or official source
Under construction1A building permit and construction seen
Permitted1A permit or filing exists; no operations seen
Planned6Announced or leased, not yet open
Reported10Named in one source, not confirmed

What no public source gives: how many cars each depot holds, how much power each one draws, and how far the average car drives empty to reach it. Charger counts leak out through permits and field visits. Electrical load and empty miles do not.

When this page is not for you

If you are looking for a job at a Waymo depot, go to Waymo’s careers page and the depot partners’ hiring pages; Flexdrive says it is hiring more than 70 people in Nashville.1

If you want to lease land to Waymo for a full depot, read Can I Lease My Land to Waymo or Tesla for a Robotaxi Depot? first, because in most cities the partner, not Waymo, signs the lease.

If your site is a small lot next to homes, Santa Monica is the warning: overnight charging there drew a nuisance order even though the noise met the code. If it is a lot or garage inside a robotaxi zone with room for a few cars, list it free.

Questions people ask

Where do Waymos go when they are not driving?

To a depot to charge and get cleaned, or to a lot near riders to wait. Waymo does not publish its waiting lots, which is why most people find them through neighbors’ complaints.

Where is the Waymo depot in San Francisco?

In the Bayview industrial area, in the southeast of the city. It is widely described as the largest operating robotaxi depot in the country, and Waymo has said it has run for about five to six years.

Does Waymo use public charging stations?

Yes, in cities where its own charging is not built yet. Waymo says it moves to dedicated charging as each city matures, and that it tries to limit and stagger its use of public stations until then.

How big is a Waymo depot?

Flexdrive’s Nashville depot for Waymo vehicles is 80,000 square feet. Waymo publishes no standard size.

Want the next depot sites in your market?

Get Depot Daily, free

Lots and yards for lease that could hold a robotaxi depot, in your market, each scored against the real depots. Your first market is free.

Your markets

Pick at least one. Your first market is free.

Free for one market. No card. One-click unsubscribe in every email.

Sources

  1. XoomPark research: robotaxi depot records, see the full robotaxi depot map
  2. The Road to Autonomy: Waymo Dallas Avis depot and active operations field report, Oct 12, 2026
  3. The Road to Autonomy: Waymo Dallas field report, Mar 30, 2026
  4. The Road to Autonomy, transcript: Building, Deploying and Scaling Autonomous Robotaxi Infrastructure

Depot counts are XoomPark’s tally of public records as of November 6, 2026. XoomPark is an independent platform. It is not affiliated with, authorized by, endorsed by or in any way officially connected with Waymo LLC, Alphabet Inc., Zoox, Inc., Amazon.com, Inc., Tesla, Inc. or any other company shown, or with any of their subsidiaries or affiliates. Company names are trademarks of their respective owners and are used here for identification only. A site or service area shown here does not mean the company works with XoomPark.