Depot throughput for an AV fleet: how many cars per hour your depot can actually turn
Which station caps the number of cars a robotaxi depot can turn in an hour, how many cars the yard should hold before extra cars only wait, and which fixes raise the number.
By XoomPark Editorial Team ·
| Station | Positions | Minutes each car holds one | Cars per hour |
|---|---|---|---|
| Gate check-in | 1 lane | 2 | 30 |
| Interior clean | 4 crews | 15 | 16 |
| DC charge | 6 stalls | 40 | 9 (the bottleneck) |
| Release check | 2 associates | 6 | 20 |
This depot turns 9 cars an hour. Cleaning could do 16 and the gate 30, but every car has to pass the chargers, so 9 is the number. Cal State Northridge's notes define the bottleneck as the resource pool with the least effective capacity, and the capacity of the whole process as the capacity of that pool.2
How do you work out cars per hour for each station?
- Charging minutes swing more than any other station. The Alternative Fuels Data Center says charging time depends on how depleted the battery is, how much energy it holds, the vehicle's onboard charger and the equipment, and ranges from under 20 minutes on DC fast chargers to 20 hours or more on Level 1.3 Use your own logged plug-in to unplug times, by car model.
- The U.S. Department of Transportation puts a DC fast charge to 80 percent at 20 minutes to 1 hour, assuming a 60 kWh battery.4 A 40-minute average sits inside that range; yours may not.
- If only some cars use a station, scale it. A station that 1 car in 4 needs is loaded at a quarter of the arrival rate. Our assumption: every car in this example gets all four stations.
- Use the station's staffed hours. Four cleaning crews on paper but two on the night shift is a different line at night.
How many cars should be in the turn at once?
In the example, a car needs 2 + 15 + 40 + 6 = 63 minutes, 1.05 hours, if nothing is ahead of it. At 9 cars an hour that gives 9 × 1.05 = 9.45, so about 9 or 10 cars in the turn keeps every station fed. With 20 cars in the turn the depot still releases 9 an hour, and by the same rule each car spends about 20 / 9 = 2.2 hours inside instead of 1.05. Our arithmetic, from the Columbia formulas.5
The same notes give Little's law, throughput equals work-in-process divided by cycle time,5 which is the quick check in the other direction: count the cars inside the gate, divide by cars released per hour, and you have the average time a car spends in the depot.
Why shouldn't the chargers run flat out all shift?
Divide the cars arriving per hour by each station's capacity. If 8 cars an hour arrive, the chargers are 8 / 9 = 89 percent busy and cleaning is 8 / 16 = 50 percent. Our assumption for planning: keep the bottleneck at or under about 80 to 85 percent of its staffed hours, and expect waits to climb fast above that. The charging queue guide works the wait times for six stalls.
What raises cars per hour at the bottleneck, and what doesn't?
| Change | Charging capacity | Depot cars per hour | New bottleneck |
|---|---|---|---|
| None | 6 × 60 / 40 = 9 | 9 | Charging |
| Unplug at target charge, 40 to 30 minutes | 6 × 60 / 30 = 12 | 12 | Charging |
| Add 2 stalls and unplug at target | 8 × 60 / 30 = 16 | 16 | Charging and cleaning tie at 16 |
| A second gate lane | 9 | 9 | Charging (no change) |
- Unplug at the target, not at full. The Department of Transportation notes that charging slows as the battery nears full and that the last 10 percent can take about as long as the first 90 percent.4 Minutes spent on that last stretch are stall minutes the next car needed.
- Check before the stall. MIT's list of ways to manage a bottleneck includes putting quality control in front of it.6 A car that fails the clean or the walk-around after an hour on a charger cost the bottleneck that hour; catch the flag at the gate and route it to the maintenance line.
- Keep the bottleneck fed. Never let a stall sit empty because the next car is still waiting at the gate or for a cleaner.
- Cross-train for the peak. Cal State Northridge's notes point to cross-training as a way to add capacity in peak periods.2 A gate associate who can move cars on and off chargers is extra stall time.
- Skip changes away from the bottleneck. A second gate lane, a faster release check or more cleaners in this example leave the depot at 9 an hour.
How do you measure cars per hour on a real shift?
- Log the hour each car clears the release check, not the hour it arrives.
- Log each car's minutes at each station for a week. The station whose capacity, positions × 60 / minutes, comes out lowest is your bottleneck, whatever the floor thinks it is.
- Compare released cars per hour with the bottleneck's capacity. Released cars well under capacity with cars waiting means the bottleneck sits idle; released cars under capacity with no cars waiting means the depot simply had fewer arrivals that hour.
- Count cars inside the gate on the hour. Divided by cars released per hour, it gives the average time a car spends in the depot.5
When this math is the wrong tool
- Cars arrive slower than the bottleneck can turn them. Then cars per hour equals arrivals, and the useful number is how long each car waits, not capacity.
- Cars take very different paths. If half go straight to charge and half need a full clean, work out each station's load from its own share of cars rather than one line.
- The depot is small. Under about 20 cars a shift, our assumption, watching the charger line is enough.
- Charging happens off site. Then the bottleneck is likely the drive out and back, and that is a routing question, not a yard one.
When depot stalls are the bottleneck at the peak, XoomPark arranges AV fleet charging at existing stations in hours their stalls sit unused, never blocks a station's regular customers and never pushes a station past its monthly peak.
Questions depot managers ask
What does throughput mean at a vehicle depot?
How do I calculate throughput time for one car?
Which station is usually the bottleneck at a depot?
Will more staff raise how many cars we turn?
How full should the chargers run?
Sources
- Stanley B. Gershwin, MIT OpenCourseWare 2.852 Manufacturing Systems Analysis: Flow Lines (Spring 2010)
- Ardavan Asef-Vaziri, California State University, Northridge: Systems and Operations Management Study Guide, Chapter 3, Throughput
- U.S. DOE Alternative Fuels Data Center: Electric Vehicle Charging Stations
- U.S. Department of Transportation, Rural EV Toolkit: Charger Types and Speeds
- Guillermo Gallego, Columbia University IEOR 4000: Throughput, Work-in-Process, and Cycle Time
- MIT OpenCourseWare 15.772J D-Lab: Supply Chains, Lecture 06: Capacity Planning and Production Flow Control (Fall 2014)
Sources are public. XoomPark isn't affiliated with the companies referenced in this post.
Authorship
Written by XoomPark Editorial Team in collaboration with Claude Opus 5.5
Role breakdown: Topic selection and publishing by XoomPark Editorial Team; research, source checks against primary sources and draft prose by Claude Opus 5.5.